StageWhat we do
IdentificationEvery device and wire is identified by a prefix-ID-suffix rule.
WiringControl wire colour and size follow circuit type and voltage: 0.75 mm² to 50 V, 1.0 mm² from 50 to 240 V, 1.5 mm² above 240 V and for potential circuits, 2.5 mm² for current-transformer secondaries. Capacitor banks are fused and cabled from a kvar table.
Factory acceptance testVisual, mechanical and electrical checks. Insulation test at 1000 V between phases and to earth. A 10-second dielectric test. Meters checked on their own forms with error percentage and sign-off.
InstallationCheck delivery and report damage within a week. Room ready: plastered, doors fitted, openings sealed, climate, lighting and clearances. Pre-check joints, barriers and earth.
CommissioningIn order: insulation test, functional simulation, logic against drawings, energise, then switch circuits one by one.
MaintenancePeriodic tightness check. Find the cause of a fault before any reset.